Replace more than a quarter of your roof covering and the work becomes notifiable. Here is what that means in practice and what it costs.
Call 07476 888638 for a free, no-obligation quote. Available Mon–Sun, 9am–6pm.
Building regulations in Wales are made by the Welsh Government and differ in places from the English versions, particularly on energy efficiency. For roofing, the key trigger is how much of the roof you are replacing.
This matters at sale time. A buyer's solicitor will ask for evidence that notifiable work was signed off, and a missing completion certificate for a ten-year-old re-roof is a routine cause of delay.
If you renovate more than 25% of the surface area of a thermal element — and a roof is a thermal element — you must bring the whole of that element up to current standards where it is technically and economically feasible.
In practice, replacing the covering on one slope of a two-slope roof is usually over the threshold. Patching a few square metres is not.
Below 25%, the work is repair and is not notifiable. Above it, the work must be notified to building control, either through your local authority or an approved inspector.
The main requirements on a domestic re-roof cover thermal performance, ventilation and structure.
The regulation asks for the thermal element to be upgraded where it is feasible. On a cold loft with an accessible ceiling, that usually means topping the loft insulation to current depth rather than insulating at rafter level — which is far cheaper and entirely acceptable.
On a room-in-roof or a warm loft, it means insulating between and over the rafters as part of the re-roof, which does add real cost. Getting this discussed at quotation stage rather than mid-job matters.
Going from natural slate to concrete tile increases the dead load on the rafters substantially. Going the other way reduces it, which sounds harmless but can affect the roof's resistance to wind uplift.
Either change should be assessed against the existing rafter sizes and spacing. On older properties in the valleys with undersized or notched rafters, this is a real consideration, not a formality.
Notifiable work is normally handled by a building notice submitted before the work starts, with inspections during and a completion certificate at the end. Fees vary by authority but are typically a few hundred pounds for a domestic re-roof.
Alternatively, a roofer registered with a competent person scheme for roofing can self-certify the work and arrange the certificate, avoiding a separate application.
Keep the certificate with your house papers. It is one of the documents that most often goes missing and most often gets asked for.
Tell us about your roofing job and we'll get back to you as soon as possible.
No. Repairs and replacement of less than 25% of the roof area are not notifiable.
A regularisation application to the local authority can retrospectively assess and certify the work, though parts may need opening up. Indemnity insurance is sometimes used instead at sale.
The requirement is qualified by technical and economic feasibility. On most homes the practical answer is upgrading loft insulation rather than a full rafter-level build-up.
Similar in structure but not identical. Wales sets its own Part L requirements, so always work to the Welsh guidance for a property in Swansea, Neath Port Talbot or Carmarthenshire.
Covering Swansea, Neath Port Talbot and West Glamorgan.